Heritage lottery fund - Parks for people project

February 2020

The Adverse Weather Conditions in February 2020 (Storm Ciara, Dennis & Jorge) have impacted on the progress of works across the park as area's remain waterlogged or flooded.

Design Team Update

Following our meeting with Harrow Council on 13th February 2020 we can confirm that our outstanding information request spreadsheet is still in place and we will continue to review these with Harrow Council to ensure they are closed off as soon as possible.

Our next formal meeting for March 2020 has yet to be confirmed. (We will continue to share information and updates with you on key dates and progress).

Anyone wishing to comment on the Park redevelopment should do so via the consultation document

Picnic Area

Works to this area commenced on Monday 06th January 2020.

The Footpath diversions to enable the deculverting works to be undertaken where put in place on 06th February 2020 and will remain in force until the works to this area are completed:

Footpath diversion

At the meeting on the Thursday 13th February 2020 we were advised by Harrow Council 4 No.additional Trees would need to be removed (1 x Birch, 1 x London Plane, 1 x White Willow & 1 x Norway Maple) as part of the Deculverting works and provision of new footbridge and footpaths these were felled on 17th February 2020. These will be supplemented by 2 No. Field Maple, 1 No. Crab Apple & 3 No. Cherry trees.

We will still press Harrow Council for the 11 new mature trees to be planted as indicated on the revised layout for this area.

Works to this area will take several months to complete and we will keep you updated on progress.

Children's Playground

Works to this area commenced on Monday 06th January 2020.

The new play equipment has now been installed and the existing equipment relocated into the designated play zones. The existing fence has now been relocated to accommodate the new layout.

We are continuing to press Harrow Council for a completion date for this area hopefully the Children's Playground will be available for the Easter Holiday.

Green Gym Relocation

The outdoor gym equipment which is currently located near the Parkside Way entrance will be located next to the Basket Ball court it is anticipated this work will commence early April 2020.

Wetland Area

Excavation works for the sedimentation ponds and reed beds is now largely complete and the work to connect these areas into the existing culvert will be completed in early March 2020 as the progress has been effected by the recent bad weather. Once the wetland site is established plants will naturally filter pollutants from the water entering the pond and reed bed and the water flowing into the Moat and Brook will be much cleaner.

Pinner View Car Park

Works to upgrade the footpath adjacent to the Moat has been completed but will remain closed until the works to the Wetland area are completed, this will link to the footpath in the Wetland area and eventually connect to the footpath in the Persimmon Homes development (Harrow West) to form part of the Green Corridor from Headstone Manor Park to Harrow Civic Centre. The vegetation along the Moat edge has been cut back to allow the new post and rail fence to be installed.

Pinner View Naturalisation

The works to the Footpath around Bessborough Cricket pitch (East & South Sections ) has now been completed however this will remain closed as the surface needs to settle down it is anticipated that this will be fully operational in early March 2020. The North & West sections are still in the early stages as they are being utilised by site vehicles accessing the park a new bench has been installed to this section which will overlook the Cricket pitch. The realignment of the Yeading Brook (North of Bessborough Cricket pitch) and the final connection to the Moat outflow has now been completed this will allow the Yeading brook to follow a more winding path which will help to control flooding and improve the aquatic improvement of the water as it meanders more slowly around the curves of the new route. This has allowed work on the landscaping to be commenced and the new Park entrance has been defined which has now been linked up to the new bridge. Works have commenced on the formation of the second bridge on this section which will link the new footpath to the Moat Cafe the anticipated completion date for this area is April 2020.

Headstone Lane West Entrance

Works on the new footpath from Headstone Lane to the Children's Playground following the route of the existing hedge is now completed and has now been reopened to the public, check out the new bench located halfway along the footpath.

Existing Footpaths (Park wide)

Work to repair / replace the existing footpaths commenced in January 2020 with completion anticipated by the end of May 2020, with the exception of works to the Parkside Way entrance as this is scheduled to commence in early Spring (June 2020) as part of the flood alleviation works.

Headstone Lane - car park

Works to this area are scheduled to commence in April / May 2020 in conjunction with the repair / replacement of existing footpaths.

Temporary Community Notice Board

Please checkout the notice board for an update on the HLF Park for people project, upcoming events in the Park & FoHMP supported events.

Monday 02nd March - Friends of Harrow Museum & Heritage Centre (Lunchtime Quiz- Moat Cafe) - 12.00 till 15.00 (Tickets available from Jenny Hamill 020 8427 2036 cost £7.50 which includes a lite lunch)

Tuesday 03rd March - Headstone Manor & Museum (Tuesday Talk - Granary) - Oh yes I remember it well 14.00 till 15.00 (Tickets available on the door Cost £4.00)

Wednesday 11th March - Wednesday Wander - Signs of Spring 10.30 till 12.00 Noon (Meet at Moat Cafe - Free)

Sunday 15th March - Headstone Manor & Museum (Granary) - Festival of Holi 11.00 till 15.00

Friday 20th March - International Day of Happiness - Spring Walk 13.30 till 14.30 (Meet at the Granary - Free)

Saturday 21st March - Headstone Manor Water Monitoring 09.00 till 10.00 (Meet outside the Moat Cafe at 08.30 if interested)

Sunday 29th March - Great British Spring Clean - Park Clean-up & Litter Pick in the Ancient Woodland 11.00 till 13.00 (Meet outside the Moat Cafe from 10.45)

January 2020

The Contractor recommenced works on Monday 06th January 2020.

Design Team Update

Following our meeting with Harrow Council on 09th January 2020 we can confirm that 20 items as detailed on our outstanding information request spreadsheet have been closed off as we have now received satisfactory responses to our questions. There are however 25 items still to be resolved, we are continuing to review these with Harrow Council to ensure they are closed off as soon as possible. Our next formal meeting will be on Thursday 14th February 2020.(We will continue to share information and updates with you on key dates and progress).

Picnic Area

Works to this area commenced on Monday 06th January 2020

At the meeting on the Thursday 09th January Harrow Council confirmed hat the Willow Tree would have to be felled to allow the Deculverting works to be undertaken we where also issued with a revised scheme for this area which would prevent the continued flooding of the area adjacent to the play ground entrance, this scheme was reviewed by the committee members on Sunday 12th January 2020, and the following statement issued

In view of concerns about both the weeping willow tree and ongoing flooding in the park a full review has been undertaken involving Friends of Headstone Manor Park, Harrow Council officers, Harrow Councillors, the National Lottery Heritage Fund, Historic England and others.

The concerns have been taken very seriously and a lot of time and effort has been spent on the review.

The design of the area has been changed as a result of the review, taking into account:

  • The health condition and longevity of the weeping willow tree and the fact that it is not classed as an ancient or heritage tree
  • River conveyancing, to move flood water more quickly away from the museum building towards the flood storage area
  • Flood risk, as deculverting the Yeading Brook creates more space for flood water
  • Positive drainage, as the whole area will drain to the Yeading Brook
  • Protection of the £1.5m investment in the park and previous investment in the museum
  • Environmental benefits, including water, ecology, habitat, and wildlife
  • Road alignment for maintenance vehicles
  • Creation of a more naturalised landscape setting by removing the full length of the culvert
  • Restoring the Yeading Brook further back in time, for heritage.

The weeping willow tree is scheduled to be felled (cut down) within the next few weeks, avoiding further delay to the refurbishment of the playground.

However the revised design allows for planting of up to 11 new mature trees. Friends of Headstone Manor Park have submitted a schedule of trees that we would like to see planted in this area this is being reviewed by Harrow Council.

We would like to thank all the local residents who have taken the time to voice their views and support the petition, which lead to this review being undertaken.

FoHMP will continue to work with Harrow Council and partners on this important project.

The Willow Tree was subsequently felled on Monday 16th January 2020, the residue material will be reused to create interesting land-forms and measures to prevent people driving illegally into the park, the site won timber will be reused to construct log walls / piles for habitat and where that is not possible it will be chipped for bedding material. Should there be any surplus material at the end of the project this will be made available for other organisations to collect.

Works to this area will take several months to complete and we will keep you updated on progress.

Children's Playground

Works to this area commenced on Monday 06th January 2020 which will mean that the Playground will be closed until Late February 2020, to allow for the existing equipment to be relocated into designated play zones and new equipment to be installed. We are continuing to press Harrow Council for a completion date for this area as it is unlikely to be completed for the Half Term Holiday

Green Gym Relocation

The outdoor gym equipment which is currently located near the Parkside Way entrance will be located next to the Basket Ball court it is anticipated this work will commence early March 2020.

Wetland Area

Excavation works for the sedimentation ponds and reed beds is now largely complete and the work to connect these areas into the existing culvert will be completed in early February 2020 as the progress has been effected by the recent bad weather. Once the wetland site is established plants will naturally filter pollutants from the water entering the pond and reed bed and the water flowing into the Moat and Brook will be much cleaner.

Pinner View Car Park

Works to upgrade the footpath adjacent to the Moat has been completed but will remain closed until the works to the Wetland area are completed, this will link to the footpath in the Wetland area and eventually connect to the footpath in the Persimmon Homes development (Harrow West) to form part of the Green Corridor from Headstone Manor Park to Harrow Civic Centre.

Pinner View Naturalisation

The works to the Footpath around Bessborough Cricket pitch (East & South Sections ) has now been completed however this will remain closed as the surface needs to settle down it is anticipated that this will be fully operational in early March 2020. The North & West sections are still in the early stages as they are being utilised by site vehicles accessing the park. The realignment of the Yeading Brook (North of Bessborough Cricket pitch) has commenced and the final connection to the Moat outflow have now been completed this will allow the Yeading brook to follow a more winding path which will help to control flooding and improve the aquatic improvement of the water as it meanders more slowly around the curves of the new route. This has allowed work on the landscaping to be commenced and once finalised will link up to the new bridge and Park entrance from Pinner View anticipated completion is April 2020.

Headstone Lane West Entrance

Works on the new footpath from Headstone Lane to the Children's Playground following the route of the existing hedge is now completed and has now been reopened to the public, check out the new bench located halfway along the footpath.

Existing Footpaths (Park wide)

Work to repair / replace the existing footpaths commenced in January 2020 with completion anticipated by the end of April 2020, with the exception of works to the Parkside Way entrance as this is scheduled to commence in early Spring (May 2020) as part of the flood alleviation works

Headstone Lane - car park

Works to this area are scheduled to commence early in 2020 in conjunction with the repair / replacement of existing footpaths

Temporary Community Notice Board

Please checkout the notice board for an update on the HLF Park for people project, upcoming events in the Park & FoHMP supported events

1 Wednesday 12th February 2020 – Wednesday Wander 10.30 till 12.00 – Trees in Winter meet at the Moat Cafe

2 Sunday 16th February 2020 - Yeading Brook Water Monitoring 10.00am till 11.00am meet outside the Moat Cafe (09.45am).

3 Wednesday 19th February 2020 - Bird Box Making - 11.00am till 15.00pm meet at the Granary

4 Thursday 20th February 2020 - Harrow Nature Heroes - Busy Birds - 10.30am till 12.30pm meet at the Moat Cafe (Registration Essential) https://www.eventbrite.com/e/harrow-nature-heroes-busy-birds-registration-open-9am-on-1st-feb-registration-91750561399

5 Wednesday 11th March 2020 - Wednesday Wander 10.30 till 12.00 – Trees in Winter meet at the Moat Cafe

6 Wednesday 08th April 2020 - Wednesday Wander 10.30 till 12.00 – Trees in Winter meet at the Moat Cafe

7 Thursday 09th April 2020 - Make a Bug B&B - 11.00am till 15.00pm meet at the Granary

Weeping Willow Tree - Update 12-01-2020

In view of concerns about both the weeping willow tree and ongoing flooding in the park a full review has been undertaken involving Friends of Headstone Manor Park, Harrow Council officers, Harrow Councillors, the National Lottery Heritage Fund, Historic England and others.

The concerns have been taken very seriously and a lot of time and effort has been spent on the review.

The design of the area has been changed as a result of the review, taking into account:

  • The health condition and longevity of the weeping willow tree and the fact that it is not classed as an ancient or heritage tree
  • River conveyancing, to move flood water more quickly away from the museum building towards the flood storage area
  • Flood risk, as deculverting the Yeading Brook creates more space for flood water
  • Positive drainage, as the whole area will drain to the Yeading Brook
  • Protection of the £1.5m investment in the park and previous investment in the museum
  • Environmental benefits, including water, ecology, habitat, and wildlife
  • Road alignment for maintenance vehicles
  • Creation of a more naturalised landscape setting by removing the full length of the culvert
  • Restoring the Yeading Brook further back in time, for heritage.

The weeping willow tree will be felled (cut down) within the next few weeks, avoiding further delay to the refurbishment of the playground.

However the revised design allows for planting of up to 11 new mature trees. Friends of Headstone Manor Park has been invited to submit suggestions regarding the species and location.

We would like to thank all the local residents who have taken the time to voice their views and support the petition, which lead to this review being undertaken.

FoHMP will continue to work with Harrow Council and partners on this important project.

January 2020

The works to redevelop the children's play ground has commenced and the area is now closed to the public.

We have been advised that works are scheduled to be completed by the 31st January 2020.

Playground works

Playground works

Playground works

December 2019

The Work site will be closed between 20th December 2019 till 06th January 2020, although some deliveries may take place on 2nd January.

Design Team Update

We can now confirm that Ground Control Ltd commenced on site on Monday 16th September 2019 and have set up there compound at the rear of the Pinner View car park. Surveys within the park have been completed and the works programme has been finalised (We will continue to share information on key dates with you).

Following our meeting with Harrow Council on 19th November 2019 we can confirm that 16 items as detailed on our outstanding information request spreadsheet have been closed off as we have now received satisfactory responses to our questions. There are however 25 items still to be resolved, we are continuing to review these with Harrow Council to ensure they are closed off as soon as possible. Our next formal meeting will be on Thursday 09th January 2020.

Picnic Area

We have held numerous meetings with Harrow Council with regards to the felling of the Willow Tree and have issued an alternative proposal that will enable the Willow Tree to be retained as well as allowing the Yeading Brook to be de-culverted. At the meeting on the 19th November Harrow Council confirmed that they are still reviewing alternative schemes and that these are not scheduled to be finalised until the end of December 2019. Works to this area are scheduled to commence early January 2020.

Detailed below are the Links to articles regarding the Weeping Willow Tree in the Harrow Times & Harrow online.

  1. Friends of Headstone Manor Park to meet with Harrow Council over willow tree - (12th September 2019)
  2. Harrow Council to fell willow tree as part of Headstone Manor Park renovation - (21st September 2019)
  3. Headstone Manor Park willow tree is fine 'in the very short term' - (25th September 2019)
  4. Harrow environment councillor says willow tree could be saved - (12th October 2019)
  5. Headstone Manor Park set for major changes in £1.3M upgrade - (04th November 2019)

Save the Willow petition now has over 1000 signatures

Children's Playground

Preparation works have commenced with the installation of new picnic benches and tables, The main works are scheduled to commence in January 2020 which will mean that the Playground will be closed until Mid February 2020, to allow for the existing equipment to be relocated into designated play zones and new equipment to be installed.

Green Gym Relocation

The outdoor gym equipment which is currently located near the Parkside Way entrance will be located next to the Basket Ball court it is anticipated this work will commence early February 2020.

Wetland Area

Excavation works for the sedimentation ponds and reed beds is now largely complete and the work to connect these areas into the existing culvert will be completed in early January 2020 as the progress has been effected by the recent bad weather. Once the wetland site is established plants will naturally filter pollutants from the water entering the pond and reed bed and the water flowing into the Moat and Brook will be much cleaner.

Pinner View Car Park

Works to upgrade the footpath adjacent to the Moat has been completed but will remain closed until the works to the Wetland area are completed, this will link to the footpath in the Wetland area and eventually connect to the footpath in the Persimmon Homes development (Harrow West) to form part of the Green Corridor from Headstone Manor Park to Harrow Civic Centre.

Pinner View Naturalisation

The works to the Footpath around Bessborough Cricket pitch (East & South Sections ) has now been completed however this will remain closed as the surface needs to settle down it is anticipated that this will be fully operational in early February 2020. The North & West sections are still in the early stages as they are being utilised by site vehicles accessing the park. The realignment of the Yeading Brook (North of Bessborough Cricket pitch) has commenced and the final connection to the Moat outflow will be completed in January 2020 (Subject to weather conditions) this will allow the Yeading brook to follow a more winding path which will help to control flooding and improve the aquatic improvement of the water as it meanders more slowly around the curves of the new route.Once completed this will allow the landscaping to be finalised with the new bridge and Park entrance from Pinner View being completed in March 2020.

Headstone Lane West Entrance

Works on the new footpath from Headstone Lane to the Children's Playground following the route of the existing hedge is now completed however this will remain closed as the surfaces need to settle down it is anticipated that this will be fully operational by early February 2020.

Existing Footpaths (Park wide)

Work to repair / replace the existing footpaths will commence in January 2020 with completion anticipated by the end of March 2020, with the exception of works to the Parkside way entrance as this is scheduled to commence in early Spring as part of the flood alleviation works

Headstone Lane - car park

Works to this area are scheduled to commence early in 2020 in conjunction with the repair / replacement of existing footpaths

Temporary Community Notice Board

Please checkout the notice board for an update on the HLF Park for people project, upcoming events in the Park & FoHMP supported events

  1. Wednesday 08th January 2020 – Wednesday Wander 10.30 till 12.00 – New Years Nature meet at the Moat Cafe.
  2. Sunday 19th January 2020 - Yeading Brook Water Monitoring 10.00am till 11.00am meet outside the Moat Cafe (09.45am).
  3. Sunday 02nd February 2020 - World Wetland Day (Family activity) 11.00 till 15.00 meet at the Football Pavilion.
  4. Wednesday 12th February 2020 – Wednesday Wander 10.30 till 12.00 – Trees in Winter meet at the Moat Cafe.
  5. Sunday 16th February 2020 - Yeading Brook Water Monitoring 10.00am till 11.00am meet outside the Moat Cafe (09.45am).

November 2019

Design Team Update

We can now confirm that Ground Control Ltd commenced on site on Monday 16th September 2019 and have set up there compound at the rear of the Pinner View car park. Surveys within the park have been completed and the works programme is being finalised (We will share this with you once it has been completed) this may be delayed as it is dependent on the outcome of the Weeping Willow Tree decision.

Following our meeting with Harrow Council on 19th November 2019 we can confirm that 16 items as detailed on our outstanding information request spreadsheet have been closed off as we have now received satisfactory responses to our questions. There are however 25 items still to be resolved, we are continuing to review these with Harrow Council to ensure they are closed off as soon as possible. Our next formal meeting will be in early January 2020.

Picnic Area

We have held numerous meetings with Harrow Council with regards to the felling of the Willow Tree and have issued an alternative proposal that will enable the Willow Tree to be retained as well as allowing the Yeading Brook to be de-culverted. At the meeting on the 19th November Harrow Council confirmed that they are still reviewing alternative schemes and that these are not scheduled to be finalised until the end of December 2019. Works to this area are not scheduled to commence until January 2020.

Detailed below are the Links to articles regarding the Weeping Willow Tree in the Harrow Times & Harrow online.

  1. Friends of Headstone Manor Park to meet with Harrow Council over willow tree - (12th September 2019)
  2. Harrow Council to fell willow tree as part of Headstone Manor Park renovation - (21st September 2019)
  3. Headstone Manor Park willow tree is fine 'in the very short term' - (25th September 2019)
  4. Harrow environment councillor says willow tree could be saved - (12th October 2019)
  5. Headstone Manor Park set for major changes in £1.3M upgrade - (04th November 2019)

Save the Willow petition now has over 1000 signatures

https://www.change.org/p/harrow-council-save-the-willow-tree-headstone-manor-park

Wetland Area

Excavation works for the sedimentation ponds and reed beds continue to progress however this has been effected by the recent bad weather, the works are scheduled to be completed by the end of January 2020 The reed bed will form a key part of the new wetland as any polluted water coming into the park will be naturally filtered and cleaned by the Aquatic plants before entering the Moat and subsequently entering the Yeading Brook.

Pinner View Car Park

Works have commenced to upgrade the footpath adjacent to the Moat when completed this will link to the footpath in the Wetland area and eventually connect to the footpath in the Persimmon Homes development (Harrow West) to form part of the Green Corridor from Headstone Manor Park to Harrow Civic Centre.

Pinner View Naturalisation

The works to the Footpath around Bessborough Cricket pitch is now well underway with several sections being completed, the remainder are still in the early stages as they are being utilised by site vehicles accessing the park. The vegetation to this area has now been removed and excavations for the realignment of the Yeading Brook (North of Bessborough Cricket pitch) has commenced. This will allow the Yeading brook to follow a more winding path which will help to control flooding and improve the aquatic improvement of the water as it meanders more slowly around the curves of the new route.

Headstone Lane West Entrance

Works on the new footpath from Headstone Lane to the Children's Playground following the route of the existing hedge is now well underway with works scheduled to be completed by the end of December 2019.

Temporary Community Notice Board

Please checkout the notice board for an update on the HLF Park for people project, upcoming events in the Park & FoHMP supported events

  1. Wednesday 11th December 2019 – Wednesday Wander 10.30 till 12.00 – Winter Birds meet at the Moat Cafe
  2. Friday 13th December 2019 - Tree Dressing 15.30 till 16.30 meet at the Weeping Willow outside the Children's Play area
  3. Sunday 15th December 2019 - Yeading Brook Water Monitoring 10.00am till 11.00am meet outside the Moat Cafe (09.45am).

October 2019

Design Team Update

We can now confirm that Ground Control Ltd commenced on site on Monday 16th September 2019 and have set up there compound at the rear of the Pinner View car park. Surveys within the park have been completed and the works programme is being finalised (We will share this with you once it has been completed) this may be delayed as it is dependent on the outcome of the Weeping Willow Tree decision.

We have tabled an outstanding information request spreadsheet following our meeting on the 03rd October 2019 with Harrow Council and this will form the agenda of our ongoing meetings the next meeting is scheduled for 19th November 2019.

Picnic Area

We have held numerous meetings with Harrow Council with regards to the felling of the Willow Tree and have issued an alternative proposal that will enable the Willow Tree to be retained as well as allowing the Yeading Brook to be de-culverted. At the meeting on the 03rd October 2019 Harrow Council confirmed that they are currently undertaking a review of the scheme for this area and will discuss these with us at our next meeting on the 19th November 2019. Works to this area are not scheduled to commence until January 2020.

Detailed below are the Links to articles regarding the Weeping Willow Tree in the Harrow Times.

  1. Harrow Times 12th September 2019
  2. Harrow Times 21st September 2019
  3. Harrow Times 25th September 2019
  4. Harrow Times 12th October 2019

Save the Willow petition now has over 990 signatures

Wetland Area

Excavation works for the sedimentation ponds and reed beds continue, these are moving along well at present and the works will be ongoing for the next couple of months.

Pinner View Car Park

Works have commenced to upgrade the footpath adjacent to the Moat when completed this will link to the footpath in the Wetland area and eventually connect to the footpath in the Persimmon Homes development (Harrow West) to form part of the Green Corridor from Headstone Manor Park to Harrow Civic Centre.

Pinner View Naturalisation

A temporary bridge has been constructed over the Yeading Brook (opposite the Pinner View car park) which has allowed work to commence on the installation of the new footpath around Bessborough Cricket pitch without site vehicles having to access the park space.

Headstone Lane West Entrance

Works on the new footpath from Headstone Lane to the Children's Playground following the route of the existing hedge will commence 4th November 2019 (Weather Permitting)

Temporary Community Notice Board

Please checkout the notice board for an update on the HLF Park for people project, upcoming events in the Park & FoHMP supported events

1 - Saturday 02nd - 6th Harrow Scouts Fireworks & Disco Evening

2 - Wednesday 09th – Wednesday Wander 10.30 – 12.00 – Autumn Winter Trees meet Moat Cafe

3 - Sunday 17th - Headstone Manor Water Monitoring – 10.00 – 11.00 meet Moat Cafe

4 - Sunday 17th - FoHMP Committee Meeting 13.00 – 15.00 meet Moat Cafe

5 - Tuesday 19th – HLF Parks for People review meeting with LBH

6 - Saturday 23rd – Nower Hill School Quiz Night

September 2019

Design Team Update

We can now confirm that Ground Control Ltd commenced the site mobilisation on Monday 16th September 2019 and have set up there compound at the rear of the Pinner View car park.

They are currently undertaking surveys within the park and finalising there works programme (We will share this with you once it has been completed)

We will continue to meet with Harrow Council on a regular basis to review any issues that may arise. (Next meeting 03rd October 2019)

Picnic Area

We have held several meetings with Harrow Council with regards to the felling of the Willow Tree and have issued an alternative proposal that will enable the Willow Tree to be retained as well as allowing the Yeading Brook to be de-culverted. Discussions are ongoing with the next meeting scheduled for 03rd October 2019.

Save the Willow petition now has over 900 signatures

Wetland Area

Landscape works have now commenced in this area and the installation of land drains along the boundary with (West Harrow Development) Persimmon Homes have been completed

Temporary Community Notice Board

Please checkout the notice board for an update on the HLF Park for people project and upcoming events in the Park

1 - Wednesday Wander - 09th October 2019 - Autumn Birds - led by Ian Jackson (RSPB)

2 - Happy Healthy Hedgehogs - 22nd October 2019 - led by Simon Braidman (Harrow Nature Heroes)

Project Newsletter

The committee are currently working on the production of a newsletter which will be utilised to communicate information regarding the project.(Further details on this item will be issued once we have meet with the Contractor).

August 2019

Design Team Update

We have been advised by LBH that the contractor Ground Control Ltd was appointed on Tuesday 13th August 2019 and pre planning meetings are scheduled for w/c 26th August 2019.

Once these have been completed we will be able to prove further information on timescales etc.

It is anticipated that mobilisation works will now commence in September 2019.

Picnic Area

We continue to challenge LBH with regards to the felling of the Willow Tree as we still fill a compromise is possible. We will continue to press LBH for a set of the finalised plans for the deculverting of the Yeading brook in this area.

Wetland Area

Works continue in this area with regards to the removal of vegetation along and the installation of Land Drainage along the boundary with (West Harrow Development) Persimmon Homes.

Temporary Community Notice Board

The notice board has now been installed on the hoarding in the Pinner View car park.

Please checkout the notice board for an update on the HLF Park for people project and upcoming events in the Park

Project Newsletter

The committee are currently working on the production of a newsletter which will be utilised to communicate information regarding the project.(Further details on this item will be issued once we have meet with the Contractor).

July 2019

Design Team Update

We have been advised by LBH that the contractor appointment that was due to have been made on Friday 26th July 2019, has now been delayed until Friday 09th August 2019 this is due to some minor issues with the procurement process.

it is anticipated that mobilisation works will not commence until September 2019.

Picnic Area

We have been advised by LBH that the Willow Tree was due to be felled in preparation of works to this area, We have strongly opposed the removal of the Willow Tree as we have not seen the finalised plans for the deculverting of the Yeading brook in this area. We believe that a compromised can be found to enable the Willow to remain, we have subsequently been advised by LBH that this work will be put on hold and discussed further with ourselves and the contractor once they are appointed.

Children's Playground

Works to the cut back low level vegetation around the perimeter of the Playground have been completed as preparation continues prior to the main works being undertaken.

Vegetation Clearance

The felled logs across the Park have now been relocated to the grassed area adjacent to toilet block all of these will be utilised during the Project. We are still pressing LBH to tidy this area as it is very unsightly and indeed is just adding to the poor impression of the park as preparation continues prior to the main works being undertaken.

Wetland Area

LBH are still in discussion with Persimmon Homes with regards to links between the park and the Harrow West Development open space.

Pinner View

We have requested LBH to rectify the damage to the temporary hoarding along Pinner View, we believe the damage is being caused by there vehicles trying to navigate into Chandlers Roofing.

We have also raised concerns with LBH with regards to sections of Pinner View being blocked by delivery vehicles this is currently being addressed by the Highways Enforcement Officer

Yeading Brook (Playground to Hugs & Giggles Nursery)

Works have been completed to enable 3 No. flood flow channels & reed beds to be installed along this section of the Brook, we have requested LBH to clean up the spoil from the grass verges as this has just been spread over the area and looks very unsightly and indeed is just adding to the poor impression of the park as preparation continues prior to the main works being undertaken.

Headstone Lane Boundary

The existing vehicle prevention barriers located along Headstone Lane have been marked for removal, we have been advised by LBH that these will be replaced by 40 large Granite boulders which have been locally sourced at nil cost to the project we however have not been advised when this work will be undertaken. we will continue to monitor this situation

We have also expressed our concern to LBH that several healthy trees have also been felled along the boundary without any prior notification, we have yet to receive a reply we will continue to seek clarification on this item.

Temporary Community Notice Board

The temporary community notice board has arrived and we are currently awaiting this to be affixed to the hoarding at the Pinner View car park.(We are still chasing LBH as to when this will be completed as the original date of 12th July 2019 has passed).

Project Newsletter

The committee are currently working on the production of a newsletter which will be utilised to communicate information regarding the project once the contractor has been appointed. the completion of this has been delayed due to the amendment of the contractor appointment. (Further details on this item will be issued once the Contractor has been appointed).

June 2019

Design Team Update

Over the month numerous contractors have visited the Park to undertake there surveys and familiarisation as the prepare there tender submissions, the Tender return date originally set for Friday 21st June 2019 was extend to Friday 28th June 2019 to enable the contractor more time to undertake a review of spoil removal following an amendment by LBH.

We have been advised by LBH that due to the extension the contract mobilisation will now be W/C 22nd July 2019. it is anticipated that works will now commence in August 2019.

Vegetation Clearance

The felled logs across the Park have now been relocated to the grassed area adjacent to toilet block all of these will be utilised during the Project. We are pressing LBH to tidy this area as it is very unsightly and indeed is just adding to the poor impression of the park as preparation continues prior to the main works being undertaken.

Wetland Area

The final section of overgrown vegetation along the boundary with the Harrow West Development (Persimmon Homes) has now been completed. LBH are still in discussion with Persimmon Homes with regards to links between the park and the Harrow West Development open space.

Pinner View

We have requested LBH to rectify the damage to the temporary hoarding along Pinner View, we believe the damage is being caused by there vehicles trying to navigate into Chandlers Roofing.

We have also raised concerns with LBH with regards to sections of Pinner View being blocked by delivery vehicles this is currently being addressed by the Highways Enforcement Officer

Yeading Brook (Playground to Hugs & Giggles Nursery)

Works have been completed to enable 3 No. flood flow channels & reed beds to be installed along this section of the Brook, we have requested LBH to clean up the spoil from the grass verges as this has just been spread over the area and looks very unsightly and indeed is just adding to the poor impression of the park as preparation continues prior to the main works being undertaken.

Headstone Lane Boundary

The existing vehicle prevention barriers located along Headstone Lane have been marked for removal, we have been advised by LBH that these will be replaced by 40 large Granite boulders which have been locally sourced at nil cost to the project we however have not been advised when this work will be undertaken. we will continue to monitor this situation

We have also expressed our concern to LBH that several healthy trees have also been felled along the boundary without any prior notification, we have yet to receive a reply we will continue to seek clarification on this item.

Temporary Community Notice Board

The temporary community notice board has arrived and we are currently awaiting this to be affixed to the hoarding at the Pinner View car park.(We have been advised by LBH that this should be completed by the 12th July 2019).

Project Newslette

The committee are currently working on the production of a newsletter which will be utilised to communicate information regarding the project once the contractor has been appointed. the completion of this has been delayed due to the amendment of the tender return date. (Further details on this item will be issued over the next few weeks).

May 2019

Design Team Update

Tender Documentation was posted on London tenders Portal on Friday 03rd June 2019, we have been advised by LBH that the completed tenders are to be returned by no later than 21st June 2019. We have been advised by LBH that contract mobilisation will be W/C 08th July 2019.

Temporary Community Notice Board

The temporary community notice board has arrived and we are currently awaiting this to be affixed to the hoarding at the Pinner View car park.

Project Newsletter

The committee are currently working on the production of a newsletter which will be utilised to communicate information regarding the project once the contractor has been appointed (Further details on this item will follow over the next few weeks).

April 2019

Design Team Update

The Quantity Surveyor has now finalised the bill of quantities and this has been reviewed by LBH for any valued engineering savings, the finalised documentation is currently with LBH Corporate Director for approval, prior to formal issue for tender. (This is currently 3 weeks behind the proposed timeline however we have been advised that the July 2019 start date will nor be effected).

Vegetation Clearance

The stored Logs adjacent to Bessborough Cricket Club outfield has now been relocated to coincide with the commencement of the Cricket season.

Moat Desilting

Phase 1 works on desilting the Moat took place over a 2 week period when approx 1000 cubic metres of silt was removed and placed in a holding pit within the proposed Wetland area. This was checked by the onsite Archaeologist and no significant finds where made. Works to the Moat have now ceased until October 2019 so as not to interfere with the planned events at The Great Barn.

Moat 1 Moat 2 Moat 3 Moat 4

March 2019

Project Timeline

The proposed project timeline has now been issued by LBH. This indicates the project commencing in July 2019.

Download the project timeline.

Wetlands Area / Moat Desilting

The vegetation to the North bank of the Moat has been cut back to allow access for the machinery to undertake the desilting, this will commence on 01st April 2019 and should be completed within 4 weeks

Design Team Update

Works on the Tender preparation are now being finalised and it is anticipated that this will be issued in accordance with the project timeline.

February 2019

Observation Survey

The Friends of Headstone Manor in-conjunction with LBH undertook an Observation Survey in the Park from Monday 11th February 2019 untill Sunday 17th February 2019. This resulted in 126 volunteer hours and 4626 visitors counted. The Data collation has been issued to LBH for them to submit to HLF.

Design Team Update

We have no further information at present we believe that the Tender package is due to be issued within the next few weeks.

Headstone Lane Car park

No further works have been carried out in this area (logs being retained on site for future use).

Picnic Area

We have been advised of the following works due to be undertaken in February have now been delayed

1 - English Oak at children's playground entrance - Monolith at 4 metres - Ganoderma and Honey Fungus visible.(attempt to retain for wildlife).

2 - Largest Weeping Willow along the frontage of playground – Reduce by 50% - (branch shed throughout upper canopy).

Both of these are to attempt to stabilise significant issues.

Pinner View

The recently removed Chestnut Pailing fence, Undergrowth and Trees on the West bank of the Yeading Brook as part of the enabling works, have now been sorted into usable and unusable piles and the clearance of unwanted materials will continue on a ad hoc basis over the coming months.

The Spinney

A 2m wide strip of ground cover along the green iron rail fence that runs parallel with the spinney on Pinner View has been cleared partly to deal with some long standing H&S issues with overhanging trees affecting the highway and electric power cables, but also to facilitate the removal of the old fence and installation of a new iron rail fence toward the end of the main works which will include the provision of the new park entrance.

Wetlands Area

The fields at the rear of the Car park & Manor House have now been fenced off to enable the vegetation along the Harrow View West development boundary, it is proposed that the fencing will remain in place until the commencement of the HLF Park for Peoples Project (Proposed start date June / July 2019) provision has been made in the fencing to enable it to be opened up to accommodate events at Headstone Manor & Museum (May Day Etc.) this will be reviewed with Headstone Manor and Museum once the main works commence.

Moat Pollution

The pollution in the moat is an ongoing issue and LBH are in conversation with the relevant parties to resolve this issue ASAP. There is a possibility that the desilting of the Moat may be brought forward to prevent issues in the Spring / Summer months.

January 2019

Observation Survey

The Friends of Headstone Manor Park in association with Harrow Council will be undertaking a Visitor Observation Survey from 11th untill 18 th February 2019.

This will tell us who is and is not using Headstone Manor Park. The observation will also be useful for measuring the impact on visitor numbers before and after any park improvements.

If you would like to assist us with this survey please contact us by email – [email protected] for further information

Design Team Update

During the Christmas Holidays we where issued with the Final Draft Tender Issue drawings which had been updated to included the items raised at the design Team Meetings in December 2018, an emergency committee meeting was held on 30th December 2018 to review these drawings as comments where required by no later than the 03rd January 2019 so that they could be included before the Design Freeze was implemented.

Our formal response was issued to LBH on the 02nd January 2019, we received confirmation from LBH on 15th January 2019 that our comments / report have been noted and included in finalising the latest drawing iteration which is now at a design freeze stage.

The pack will be sent to the HLF Project Officer and Mentor for review and approval prior to going to the Quantity Surveyor for cost estimating.

Headstone Lane Car park

The removal of the Cypress Lawson (Non Native species) trees behind Hugs and Giggles has now been completed with the logs being retained on site for future use.

Picnic Area

The removal of the trees adjacent to the footpath to Bessborough Cricket Pavilion and the right hand side of the changing rooms has been completed with the logs being retained on site for future use

We have been advised of the following works that will be undertaken in February 2019.

1 – English Oak at children’s playground entrance – Monolith at 4 metres – Ganoderma and Honey Fungus visible.(attempt to retain for wildlife). 2 – Largest Weeping Willow along the frontage of playground – Reduce by 50% – (branch shed throughout upper canopy).

Both of these are to attempt to stabilise significant issues.

Pinner View

The Existing Chestnut Pailing fence on the West bank of the Yeading Brook and associated overhanging branches of trees have been removed as part of the enabling works

The Spinney

The existing Fence on the North Elevation is being removed as part of the enabling works this is being replaced by Harris fencing on the proposed new fence line South of the Yeading Brook this equates to circa 10% of the Spinney being brought back into the Park

December 2019

Design Team Meting – Moat

The de-silting of the Moat and associated license (U1 / D1 exemptions etc),are in place and all works must be completed in accordance with Historic England letter dated 21st December 2017 Ref; S00181874.

The vegetation around the Moat can be removed to ground level only no grubbing out or poisoning of roots due to the proximity of the water course. Existing trees are to be retained and crown lifted where necessary.

The existing Chestnut palings are to be removed and replaced. The fence along the footpath (Car park) will be Post & Rail construction the remaining will be Post & Wire construction this will be infilled with native species hedging to complete a protective barrier.

The existing vegetation mound bordering the car park will be stripped of vegetation and reduced in height by approx 0.5M.

Three proposals for the sluice gate arrangement will be forwarded to Historic England for there approval along with a proposal to prevent silt from first flood entering the Moat via the existing culvert

Design Team Meeting – Picnic Area

The existing Willows in this area will be retained until September 2019 as the provision of a single pond in this area is not achievable due to the current Brook flow rates a revised scheme is currently being designed this will probably contain 3 separate sections (1 small pond & 2 areas of aquatic planting)

Design Team Meeting – Children’s Playground

The following items will be refurbished and brought back into full operation

  • Galactic Climbing Frame
  • Roundabout
  • Chair Swing
  • Tea Cup

It is proposed that 3 new pieces of equipment will be purchased

  • Toddler Swing
  • Large Slide
  • Zip Wire

The layout of the Playground will be split into 4 separate zones (2 children’s, 1 team play & Zip Wire)

Design Team Meeting – Boundary with Harrow View (West) – Kodak Site

It was confirmed that there would be no formal demarcation line from HMP & HV(W) upon completion of the project the existing steel fence will be removed and the existing drainage ditch infilled to align the different ground levels.

Design Team Meeting – Pinner View

The existing outlet from the Moat to the Brook will be replaced with a flexible pipe the outlet from the attenuation tank will also be connect into this new pipe section and the surrounding ground level will be landscaped this increase the amount of space available to the left hand side of the Cafe which could then be utilised by the Museum as Picnic space it is also proposed that a crossing be installed at this point to connect to the new foot path adjacent to Bessborough Cricket pitch.

The proposed splitting of the Brook into 2 Channels was reviewed and in principal it was agreed that the single channel would be retained due to the current Brook flow rates,the channel would however be diverted towards Pinner View with the sloping edge to allow pond dipping access formed on the park side, this will enable the existing trees adjacent to Bessborough Cricket pitch to be retained the new footpath would then be installed within the existing tree line.

The boundary with Pinner View would be protected by Earth Mounds and existing Boulders (Set at Max 1.0M intervals) to prevent unauthorised vehicular access.

Design Team Meeting – Updated Drawings

It is proposed that the next issue of drawings would by the end of December (This would be the final issue for comment before the Tender Package is formulated)

November 2018

Pinner View – Enabling Works

The works commenced in November 2018 on the section of park grounds opposite Headstone Manor Museum Office and car park the removal of trees / shrubs / under-story vegetation will enable Harrow Council to fully access the existing tree stock to enable the full extent of tree felling that will be required to be undertaken for the wetland element of the project also to determine if any of the tree stock can be preserved or worked around during the wetland project.

A vast majority of the tree / logs and shrubs were in such poor condition and also had a lot of fly tipped waste tangled within it, Harrow Council decided to clear most of the site while they had the chance with the plant and contractor on site at this time. A representative from Harrow Council has been onsite to supervise and ensure the boundary to the site is protected by the remaining tree / logs and boulders, until the Heras fencing panels have been installed this will protect the area from the old parks vehicle car park to the Yeading Brook channel adjacent to the visitor centre.

At the same time Harrow Council has been able to demolish the BMX site and remove all the contamination i.e. fridges, fridge freezers, vehicle tyres, wheels and other vehicle parts which had been a major cost risk to the project; the site is now clear, leveled and ready for the main project works.

It is intended that these works will be completed by the end of November 2018

Design Team Meeting

Representatives from FoHMP attended the first design team meeting and was pleased to see that the reports issued to Harrow Council in September 2018 had been issued to the design team and that relevant items in relation to the project have been taken on board and that a vast majority will be taken into consideration in the final scheme.

The FoHMP where tasked with undertaking a survey of the existing park furniture for issue to the design team for inclusion in the next phase of the design (Hopefully all park furniture will be replaced as part of the project). The survey was undertaken and issued to Harrow Council & Design team on 09 November 2018.

The current design is being updated and it is intended that the updated drawings will be available for FoHMP to review by the middle of December 2018

October 2018

Headstone Lane Car Park

The works commenced in October 2018 with the removal of non native trees and those in poor condition, this has been done to increase clear site lines into the park & car park so that police can see into the park & car park and be more vigilant of some of the anti social problems that are continually being reported to Harrow council.

In addition these works will enable Harrow council to undertake the resurfacing of the car park as well as line marking parking bays. Harrow council are confident that the removal of the trees will prevent any future damage to the car park surface due to tree root ingress, there will also be improvement to the footpath and paving around the nursery pavilion to prevent ponding during bad weather.

The existing Wire fencing and boundary posts will also be removed and replaced with a softer landscaped mound to separate the park from the car park area

In consultation with FoHMP, Hugs & Giggles Nursery & Local residents Harrow Council have agreed to remove the Lawson Cypress trees at the rear of the nursery building which are in poor condition and are susceptible to storm damage, this will also help prevent any potential damage to the Nursery drainage and also increase light levels into the gardens and homes adjacent to the park boundary.

It is intended that the tree works will be completed by February 2018 (this is being done on an as and when basis to keep the cost down), the resurfacing works, line marking and landscaping will follow at a later date (Some of this work is dependent on materials being utilised from the HLF Parks for People Project)

September 2018

During September the FoHMP undertook the following surveys / reviews and forwarded them to Harrow Council as part of the design process

1 – Park Inspection 2 – Review of initial Drawings for Park Refurbishment 3 – Review / Observation of Green Flag Status 4 – Dog Walkers Questionnaire